08.18.22 Town HallWelcome to the August 18, 2022,
Prosper Town Council
Town Hall Meeting
Welcome and Introductions –Mayor David F. Bristol
Tonight’s Agenda
•Update on Town Road Projects
•Hulon Webb, P.E. –Interim Executive Director of Development and
Infrastructure Services
•Update on Texas Department of Transportation (TxDOT) Projects
•Travis Campbell, P.E. –TxDOT Denton County Area Engineer
•Update on North Texas Tollway Authority (NTTA) Projects•Rachel Kulhavy, P.E. –Resident Engineer•Kelly Johnson, P.E. –Senior Manager of Project Development
•Windsong Ranch Land Acquisition
•Dan Baker –Director of Parks and Recreation
•Questions / Comments
Update on Town Road Projects
FM 2478 / Custer RoadFM 1385Dallas North TollwayUS 380 / University Drive
FM 1461 / Frontier Parkway
Denton
County
Collin
County
Artesia MUD
Parvin Road
Town of Prosper: 27 Square Miles
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
2010201120122013201420152016201720182019202020212022202420252026202720282029203020319,350 10,560 12,190 13,380 14,710 15,970 17,790 20,160 22,650 25,650 28,380 31,090 35,430 42,094 45,883 50,012 54,513 59,420 64,767 70,596 76,950 POPULATIONYEAR
Prosper Population Growth
Town of Prosper = 220.2% Growth
Denton County = 36.8% Growth
•Comparison to Texas = 15.9%
•Comparison to U.S. = 7.4%
2010 Census to 2020 Census
Town of Prosper Thoroughfare Plan
FM 2478 / Custer RoadFM 1385Dallas North TollwayUS 380 / University Drive
FM 1461 / Frontier Parkway
Parvin Road
FM 2478 / Custer RoadFM 1385Dallas North TollwayUS 380 / University Drive
FM 1461 / Frontier Parkway
Parvin Road
Regional Partnerships
Dallas North TollwayUS 380 / University Drive
Parvin Road
FM 1385Teel ParkwayFishtrap Road
Gee RoadLegacy RoadLocal Partnerships
Dallas North TollwayUS 380 / University Drive
Parvin Road
FM 1385Teel ParkwayFishtrap Road
Gee RoadLegacy RoadIn The Works
Kickoff
30% Design
60% Design
90% Design
100% Design
ROW and Utility
Relocation
Complete
Advertising
( 30 days)
Open Bids
Council Award
(30 days)
Notice to Proceed
Construction
Identify R/W needs/Confirm eminent domain requirement
Identify conflicting utilities
Verify budget/match to new development
Complete usual R/W acquisition/Process eminent domain
Notify conflicting utilities
Verify budget/match to new development
Release for Utility Relocation
Complete Eminent Domain
Verify Budget/match to new development
Budget available for engineer estimate
Complete contract documents
Assign Project Team
Confirm project intent
Contract with design
engineer
ID R/W needs/ED
Event Driven (typically
up to 18-24 months)
Time Driven
(typically 3-6
months)
Budget available
Proper bids/Bid tabulation
Qualified bidder
Bonds
Contract documents
complete within 30 days
Insurance
Pre-Construction meeting
Pre-Bid Meeting
Addendums
Proper advertising
Note: Do not
proceed past
arrows unless
all items are
completed.
Inspections
Change order tracking
Project closeout
Design/Permitting
ROW/Utility Relocations
Bidding/Construction
1. Fishtrap (Stuber Elementary –DNT)
•Existing 2-
lane asphalt
•Design
started 2020
•Engineer’s
Estimate:
$20M
1. Fishtrap (Stuber Elementary –DNT)
•Construct 4
lanes with
median
landscaping
•Bid July 2022:
$26.8-$29M
•Bid Award:
August 23, 2022
•Construction:
Sept/Oct 2022 –
Spring 2024
2. Gee Road (Windsong Retail –Fishtrap Road)
Fishtrap Road (Gee Road –Teel Parkway)
•Existing 2 lanes
•Gee Road
ultimate 6 lanes
•Fishtrap Road
ultimate 4 lanes
•Designed early
by Developer
•Engineer’s
Estimate: $8.9M
2. Gee Road (Windsong Retail –Fishtrap Road)
Fishtrap Road (Gee Road –Teel Parkway)
•Construct 4 lanes
with median
landscaping
•Bid July 2022:
$10.3-$14M
•Bid Award:
August 23, 2022
•Construction:
Sept/Oct 2022 –
Summer 2023
•Includes signal at
Windsong/Fishtrap
3. Teel/US 380 Intersection Improvements
•Design Complete
•ROW Acquisition Underway
•Engineers Estimate: $1.5M
•Construction: Winter 2022/2023 -Fall 2023
2022
Proposed
Denton
County
Bond
Projects
https://www.prospertx.gov/business/land-development/engineering/construction-updates/
Update on TxDOT Projects
Town of Prosper Town Hall Meeting August 18, 2022
TxDOT Projects:
Denton County
Travis Campbell, P.E.
Denton County Area Engineer
July 7, 2022
Town of Prosper Town Hall Meeting August 18, 2022
Safety Moment –Work Zone Awareness
Town of Prosper Town Hall Meeting August 18, 2022
US 380 Improvement Project Overview
▪Description:Widen US 380 from four
to six lanes, add curbed median,
sidewalks and grade separations at
major intersections including:
–FM 720/Oak Grove Lane
–Navo Road/Union Park Boulevard
–FM 423/Gee Road
–Teel Parkway/Championship Drive
–Legacy Drive
▪Limits:10.5 miles from US 377 to
west of County Road 26 (Collin County
line)
▪Construction Cost: Approximately
$140 million
▪Contractor: Zachry Construction Corp.
Town of Prosper Town Hall Meeting August 18, 2022
US 380 at Paloma Creek Boulevard (At-Grade
Intersection)
Town of Prosper Town Hall Meeting August 18, 2022
US 380 at FM 423 (Grade Separation Intersection)
Town of Prosper Town Hall Meeting August 18, 2022
Project Phasing
Phase 1 -Traffic will shift to the north side of US 380. Crews will
install traffic barrier to separate the work zone from the travel lanes.
The work zone will be on the south side of US 380 where road
widening will occur. Phase 1 work is expected through the end of
2022, weather permitting.
Town of Prosper Town Hall Meeting August 18, 2022
Project Phasing
Town of Prosper Town Hall Meeting August 18, 2022
Planning Projects: Denton County
30
Widen and reconstruct FM 1385
from a 2-lane urban undivided to
4/6 lanes urban divided from US
380 to FM 455. Re-align
intersections at Mustang Road and
Gee Road.
1315-01-0301
TOTAL COST: $169,058,671
1
Town of Prosper Town Hall Meeting August 18, 2022
Thank You!
31
TxDOT –Dallas District Planning
Maps are Updated Quarterly and
can be found here.
Travis Campbell, P.E.
TxDOT Denton County Area Engineer
Travis.Campbell@txdot.gov
Update on NTTA Projects
CONSOLI DATED
PERF ORMANCE
METRICS
HORATIO PORTER, FINANCE
PRESENTED TO:
BOARD OF DIRECTORS
OCTOBER 10 , 2016
NTTA.org
Rachel Kulhavy, P.E.
Resident Engineer, NTTA
Kelly Johnson, P.E.
Senior Manager of Project Development,
NTTA
August 18, 2022
Dallas North Tollway ExtensionPhase 4
34
DNT Phase 4
Project Phases
•DNT extension over US 380
•Construction began Feb. 2020
•DNT Phase 4A: US 380 to FM 428
•Design began Dec. 2021
•DNT Phase 4B: FM 428 to the
Grayson County line
Overview
The planned DNT Phase 4 Corridor
Project will extend the tollway north
from US 380 to the Grayson County
line.
2
DNT Mainlane
Extension over
US 380
•Current work consists of:
•Substructure work
•Concrete paving
•Electrical work
•PGA Pkwy bridge work
2
DNT Mainlane
Extension
North of US 380 to South of
FM428
•Environmental work is
complete
•Design is now underway
•Construction anticipated to
start in early 2024
Our Mission
North Texas Tollway Authority
Windsong Ranch Land Acquisition
•Purchased for $3,827,600
•Will be preserved as parkland
•Future Master Plan / Community Input
Meetings to determine needs
•Potential location for Fire Station
•Tellus Group will continue to maintain
600 acres of open space in the area
•Interim Uses
•Mown Trail
(similar to Raymond Community Park)
•Parking / Access Improvements
•Off Road Bike Trails
Questions / Comments
Closing Remarks –Mayor David F. Bristol