20180828 Police Station and DispatchMEETING
AUGUST 28TH, 2018
6:00PM
TOWN OF PROSPER POLICE STATION & DISPATCH
CONCEPTUAL DESIGN
BASELINE SCHEME
BASELINE SCHEME
BASELINE SCHEME
ENHANCED SCHEME
ENHANCED SCHEME
ENHANCED SCHEME
ORIGINAL PROJECT SCHEDULE
•Receive Design NTP from Town Council June 26, 2018
•Anticipated CMaR on-board July 24, 2018 or August 28, 2018
•100% Schematic Design September 20th, 2018
•100% Design Development December 13th, 2018
•100% Construction Documents March 1, 2019
•Bidding April, 2019
•CMaR Construction Contract NTP May, 2019
•Substantial Completion (anticipated)July 2020
PROJECT SCHEDULE –CMaR ON BOARD 9/11
•Receive Design NTP from Town Council June 26, 2018
•Anticipated CMaR On-board July 24, 2018 September 11, 2018
•100% Schematic Design September 20, 2018 October 4, 2018
•100% Design Development December 13, 2018 January 10, 2019
•100% Construction Documents March 1, 2019 March 29, 2018
•Bidding and GMP April, 2019 April-May, 2019
•CMaR Construction Contract NTP May, 2019 June, 2019
•Substantial Completion (anticipated)July, 2020 August, 2020
PROJECT SCHEDULE –COMPETITIVE SEALED PROPOSAL
•Receive Design NTP from Town Council June 26, 2018
•Change Order for Cost Estimating July 24, 2018 September 11, 2018
•100% Schematic Design September 20, 2018 October 4, 2018
•100% Design Development December 13, 2018 January 10, 2019
•100% Construction Documents March 1, 2019 March 29, 2018
•CSP Bidding April, 2019 April-May, 2019
•*Possible V.E. if bids over Budget May -June, 2019
•Construction Contract NTP May, 2019 July, 2019
•Substantial Completion (anticipated)July, 2020 September, 2020