20160126 Prosper Town Hall - Council Update 1 26 16 (Council)The Town of Prosper
Town Hall/Multi-Purpose Building
Council Update
Schematic Design
January 26, 2016
Specialists in Municipal and Public Architecture
Proposed Exterior
Design
•
•
•
•
•
•
•
•
•
•
•
•
Scheme A
(Original -Brick with
Metal Ends)
Scheme B
(Brick & Stone Ends)
Scheme C
(Brick, Stone &
Metal Ends)
Scheme D
(Brick & Stone Ends
with Metal Portal
Building Lobby
Sketches
Floor Plans
Project Schedule
Design Development Documents 2 months
Pricing Documents 2 months
CMR GMP & 100% CD’s 1 month
Construction Phase 15 months
Total Remaining 20 months
Estimated Building Occupancy Oct. 2017*
*Decisions needed to achieve this scheduled completion date:
•Approval of the Floor Plans, Site Plan and Exterior Renderings by
Jan. 26, 2016
•Approval of the Estimated Cost of Construction by Jan. 29, 2016
•Approval of the CMR’s Guaranteed Maximum Price by July 8, 2016