20160126 Prosper Town Hall - Council Update 1 26 16 (Council)The Town of Prosper Town Hall/Multi-Purpose Building Council Update Schematic Design January 26, 2016 Specialists in Municipal and Public Architecture Proposed Exterior Design • • • • • • • • • • • • Scheme A (Original -Brick with Metal Ends) Scheme B (Brick & Stone Ends) Scheme C (Brick, Stone & Metal Ends) Scheme D (Brick & Stone Ends with Metal Portal Building Lobby Sketches Floor Plans Project Schedule Design Development Documents 2 months Pricing Documents 2 months CMR GMP & 100% CD’s 1 month Construction Phase 15 months Total Remaining 20 months Estimated Building Occupancy Oct. 2017* *Decisions needed to achieve this scheduled completion date: •Approval of the Floor Plans, Site Plan and Exterior Renderings by Jan. 26, 2016 •Approval of the Estimated Cost of Construction by Jan. 29, 2016 •Approval of the CMR’s Guaranteed Maximum Price by July 8, 2016